Modular Mindset
Weekly

by Thatcher Butcher

Your Questions - Answered

Six Questions I Get Asked Every Week

I said I’d answer questions this week. Here are the ones that come up most often on first phone calls — the same six, more or less, in the same order.

If yours isn’t here, send it, and I’ll get to it.

1. "How long does it actually take?"

The answer is that the factory part is the short part, and almost nobody expects that.

Production itself is fast — a building moves through the plant in a matter of weeks, not months. What takes time is everything in front of it: design and engineering, third-party plan review under your state’s program, procurement of anything with a long lead time, and getting onto the production calendar.

So when somebody asks how long it takes, the real question is when you can freeze the design, because that’s the clock that matters. Come to us with a set of drawings that are still being refined and the answer is “I don’t know.” Come with a design freeze you can hold, and we can give you a date.

That’s the whole reason I wrote a post about the freeze a few weeks back. It’s not paperwork. It’s the schedule.

Thatcher Butcher

Thatcher Butcher

President, KBS Builders, Inc.
tbutcher@kbs-homes.com

2. "Can you build my architect's design?"

Usually, yes — with one condition, and it’s better raised early than late.

Modules have to fit on a truck and travel roads legally. That sets a maximum width, and the module lines have to land somewhere sensible in the plan. An architect who knows that from the first sketch gives up almost nothing. An architect who finds out at 90 percent drawings has to make compromises, because now we’re adjusting a design that was nearly complete.

So the real answer to this question is: bring us in at schematic. Not to take the pencil away from your architect — to tell them where the mate lines should be while moving them is still free.

There’s also a version of this question people don’t ask out loud, which is “will it look like a factory built it?” No. Once it’s set and buttoned up, you can’t tell from the street, and neither can an appraiser.

3. "Isn't the quality lower?"

I’d argue it’s better. The building is built to your state’s code, inspected by our in-house QC team in the plant, inspected by a third party in the plant, and inspected again at the site. Our inspectors are present in our factory continuously. Imagine if that were the case for site-built. A factory gives you consistency — the same person doing the same task the same way, on a jig, in the dry, with the materials already staged. Unit 40 gets built the way unit 1 did.

The other thing nobody mentions: our materials don’t sit outside for months. Lumber that’s been rained on for weeks before it’s covered is a real and common problem on site, and it doesn’t happen here.

I won’t claim perfection. Buildings are built by people. But if you’re comparing a factory to a jobsite in February, it isn’t close.

4. "What happens if something's wrong when it shows up?"

This is the question that separates people who’ve done a modular project from people who haven’t, and I wish more first-timers asked it.

Things happen. A module travels down the highway; occasionally something shifts. The question isn’t whether you’ll ever have an issue — it’s who owns it and how fast it moves.

Get that in writing before you sign. Who’s responsible for what at the mate line. Who does the punch. What the response time looks like. How warranty works, and for how long. A manufacturer who gets cagey on that question is telling you something.

I’d rather have an uncomfortable conversation about it in month one than a lawyer in month twelve.

5. "Do modular homes appraise and resell like site-built?"

A modular home on a permanent foundation is real property. It’s built to your state’s code, it’s taxed like the house next door, and it’s bought and sold like the house next door.

The confusion here isn’t really about buildings. It’s about words — the fact that “modular,” “manufactured,” “prefab,” and “factory-built” get used as if they mean the same thing when they don’t. That’s the argument I made a few weeks ago about the chassis rule, and it’s why I keep pushing people to say the code rather than the marketing term.

If you’re a builder and an appraiser or a lender is treating your modular project as something it isn’t, the fix is almost always documentation: what code, what inspection, what foundation.

6. "Can you do custom?"

Yes, we do frequently. But I’d want you to understand what you’re buying.

Repetition is where factory economics live. A building with four unit types is a different price than a building with eleven, and a one-off custom house is a different price than a plan we’ve run before. Not because we’re penalizing you for it — because every new configuration is its own engineering, its own approval, and its own first-time-through on the floor.

So custom is available, and on a single home it’s often the right call. On a large project, every unit type you can eliminate is money back in your pocket. If you want one lever to pull, that’s it.

The pattern

Look at those answers together, and they allude to the same thing: the decisions that determine how a modular project goes are made earlier than you’re used to making them.

That’s it. That’s the whole business. Modular doesn’t remove work or complexity — it moves both of them upstream, where they’re cheaper to deal with. Every question above is really a question about how early you’re willing to decide.

Next week: winter sets. It’s fall, which means anybody planning to set between November and April should be thinking about it now, and there are a handful of things that make the difference between a good winter set and an expensive one.

Keep the questions coming.

— Thatcher